2. A certain project can be completed by 10 workers in 45 days. In order to complete the project
sooner, the company plans to hire additional workers. How many workers are needed to complete the
project in 25 days?
Solution​


Sagot :

Answer:

The project needs 18 workers to be done in 25 days.

Step-by-step explanation:

the project is 10 workers × 45 days = 450 "work" divided by the workers in days

this "450 work" needs to be done in 25 days so there's a need for 450/25 = 18 workers to do the work

thus, they need to add 8 more workers

10 workers × 45 days = x workers × 25 days

10 workers × 45 days ÷ 25 days = x workers

x workers = 18 workers