15 workers can finish a job in 100 days. The job needs to be finished in 60 days. How many workers are needed for the job to be finished in 60 days.

Sagot :

Answer:

25 workers

Step-by-step explanation:

man. days = man. days

15(100)=x(60)

1500=60x

x=25